State of Kerala & Anr. Etc. Etc. Vs. M/s. RDS Project Ltd. & Ors. Etc. Etc.
State of Kerala
& Anr. Etc. Etc. Vs. M/s. RDS Project Ltd. & Ors. Etc. Etc.
[Civil
Appeal Nos. 3239-3246 of 2020 arising out of S.L.P. (C) Nos. 3008-3015 of 2020]
R.F.
Nariman, J.
1)
Leave granted.
2)
Heard Mr. K.K. Venugopal, learned Attorney General for India appearing on
behalf of the State of Kerala, Dr. Abhishek Manu Singhvi, learned Senior
Counsel for the Respondent No.1, Mr. Gopal Sankaranarayanan, learned Senior
Counsel for the Respondent No.3, Mr. Jaideep Gupta, learned Senior Counsel for
the Respondent No.2, Mr. Rana Mukherjee, learned Senior Counsel for the
Respondent No. 9 and Mr. V. Giri, learned Senior Counsel for the Respondent
Nos. 4 & 5. The impugned High Court judgment dealt with a project called
the Palarivattom Flyover on the National Highway, Cochin City, State of Kerala.
This
was constructed by Respondent No.1 and inaugurated on 12.10.2016. However,
after one year of this Flyover being used, the Consultancy Agency for the
Ministry of Road Transport and Highways, Government of India, on regular
inspection of the bridge, reported on 16.03.2018 that the bridge was in a
distressed condition with several cracks as a result of which measures should
be taken to rehabilitate the flyover.
The
IIT, Madras, was thereafter appointed as an expert agency which delivered
several reports in which, according to it, the bridge could follow a carbon
fibre fabric composite treatment and be repaired instead of being demolished.
Meanwhile, Dr. E. Sreedharan submitted a report to the Chief Minister of Kerala
on 03.07.2019 in which he recommended the strengthening and replacement of RCC
girders with PSC girders to ensure durability which would necessitate a
demolition and re-construction of the bridge. Dr. E. Sreedharan, by a report
dated 14.09.2019, referred to the IIT reports and did not agree with the same,
stating that if his plan was to be carried out, a 100 year guarantee would be
given for the newly constructed flyover.
3)
Given these divergent streams of opinion, the State Government then set up a
High Level Committee consisting of five persons who are as follows:-
1.
Sri Ashok Kumar M. (Convenor)
Chief Engineer, National Highways,
Public Works Department
Thiruvananthapuram
2.
Sri S.Mano Mohan (Member)
Chief Engineer, Bridges,
Public Works Department
Thiruvananthapuram
3.
Sri M.N. Jeevaraj (Member)
Chief Engineer (Rtd.),
Public Works Department
Thiruvananthapuram
4.
Sri S. Saju (Member)
Senior Bridge Engineer,
Public Works Department
Thiruvananthapuram
5.
Sri S.M. Ashraf (Member)
Senior Structural Engineer,
Public Works Department
Thiruvananthapuram
4)
It will be noticed that apart from experts who were engineers, one of whom was
a Senior Bridge Engineer, a Senior Structural Engineer of the PWD was also a
member of this Committee. This Committee went into the IIT reports and the
Sreedharan report in some detail, after which it concluded as follows:
"9.
Conclusion
"a.
The tests carried out by IIT Chennai are as per IS codes and IRC
recommendations. IIT Chennai being a premier and reputed institution, their
findings can be accepted and relied on. However, a load test as specified in
IRC 112:2011 has not been proposed by IIT Chennai.
The
reasons are not mentioned in their report. The Committee feels that since crack
width in certain girders have exceeded the allowable limits which is one of the
compliance criteria for load test, IIT might have decided that there is no
point in doing a load test before strengthening. However, IIT has recommended
load test after strengthening the flyover.
IIT
has suggested its scheme for strengthening the flyover, which again is as per
IRC recommendations. But, IIT has not mentioned the service life of the flyover
after strengthening. IRC also does not recommend service life of any structure
after doing the strengthening works proposed by IIT.
b)
As mentioned by Dr. E.Sreedharan a new construction with proper design, with
quality execution of the work with quality materials and strict technical
supervision can expect a service life of 100 years.
c)
Construction cost of the proposal of demolishing and replacing of
superstructure as proposed by Dr.E. Sreedharan will cost (18.71 crores), more
than double the cost estimated for the strengthening scheme proposed by IIT
(7.31 crores). The required completion time for both cases is almost the same.
d)
Normally rehabilitation/strengthening are required for old as well as
distressed bridges having service life of 40 years or more and also
strengthening works are normally required for limited members or locations of a
flyover/bridge. In the case of Palarivattom flyover as per the findings of IIT
Chennai, 97 RCC girders out of 102 girders requires strengthening which is an
extensive strengthening work for superstructure. Based on the all the above
factors, Committee is of the opinion that considering the service life assured
by Dr.
E.
Sreedharan for 100 years, it is better to accept the proposal by him."
5)
The State of Kerala, by a G.O. dated 25.10.2019, examined this High Level
Committee Report, and accepted it, stating as follows:
"6.
Government have examined the whole matter in detail and have decided to accept
the recommendations of the Technical Committee and to proceed accordingly. It
is also decided to accept the letter of offer made by Delhi Metro Rail
Corporation to take over the bridge for rehabilitation as per letter read as
6th above. DMRC shall submit detailed item wise estimate for approval of
Government. On the basis of the detailed estimate, Finance Department shall
allot funds in the appropriate Head of Account for the purpose. RBDCK will hand
over the bridge site to DMRC free of all encumbrances.
7.
RBDCK shall realize the loss sustained to the Government from the contractor in
the light of the report of IIT Madras, report of Dr. E.Sreedharan and the FIR
filed in case No. 1/2019 of Moovattupuzha Vigilance Court and as per the relevant
provisions of the agreement. RBDCK shall also initiate action against the
contractor for the lapses as per PWD Manual.
8.
This order will be subject to the final decision of Hon'ble High Court in WP
(C)s 25343, 25362 and 26405 of 2019."
6)
At this point, a Writ Petition was filed by the Respondent No.1 in the Kerala
High Court against the aforesaid G.O. By the impugned judgment, the Kerala High
Court went into the terms, in particular, clause 11 of the original tender
between the contractor- Respondent No.1 and the State, and then considered the
various reports.
The
High Court also noticed that a vigilance enquiry had been conducted because
there were allegations that there was large scale corruption, and as part of
it, a team of experts from the Government Engineering College, Trichur reported
that there are 2183 cracks on the girders out of which 99 cracks are above 0.3
mm width and 83 cracks on pier caps out of which 5 cracks are about 0.3 mm
width.
7)
After considering the arguments of counsel appearing for all parties, including
the Respondent No.3- KITCO, stating that a load test is extremely necessary for
the purpose of ascertaining the strength of the flyover before anything further
is done to it, the High Court concluded: "19. There is no dispute about
the fact that as per the terms of contract between the parties, load test is a
requirement to be performed to ascertain the strength of the bridge and to
ensure that it has the expected strength.
According
to the contractor, though certain cracks have developed in the girders, it
needs only repairs which the contractor is willing to do and it would not
affect the strength of the bridge in any way. A similar view had been expressed
by the consultant M/s KITCO as well. According to them, the load test is
mandatory to ascertain the strength of the bridge, and if the girders and
platform are demolished, such an opportunity will be lost.
The
Government and its authorities are not in favour of a load test since they feel
that the aforesaid cracks itself are enough to arrive at a conclusion that
those girders are to be demolished. Government had already taken a decision to
remove the platform and girders. Once it is removed and demolished, it may not
be possible to ascertain the strength of the present structure, which may
prejudicially affect the right of all the stakeholders, including the
Government.
The
contractor as well as the consultant still believes that the load test would
prove that there is no requirement for demolishing the structure. Therefore,
before demolishing the platform and the girders, it is better to have a load
test conducted, to avoid any further controversy in the matter. After
conducting such load test, it shall be open for the Government and its
authorities to take a decision whether they should proceed in accordance with
the manner in which they have already decided or to take a different approach
in the matter. In the result, the following directions are issued.
(i)
That the Government shall conduct a load test of the Palarivattom flyover
through an approved qualified agency capable of conducting such a test, with
notice to all the stakeholders.
(ii)
The entire expenditure for conducting the load test shall be borne by the
petitioner in WP (C) No. 26030/2019.
(iii)
The entire process shall be completed within a period of three months or at an
early date, as may be possible.
(iv)
After conducting the load test, the Government shall file a statement before
this Court along with the report of the concerned agency."
8)
Having perused the High Court judgment, what is clear is that the High Court,
instead of applying the well-established parameters of judicial review and
ascertaining whether the decision of the State Government would violate Article
14, went into the matter itself and stated that it is better to have a
"load test conducted to avoid any further controversy in the matter".
9)
Given the fact that an Expert Committee, which is a High level Committee of
five experts was set up to go into the divergent opinions of IIT Madras and Dr.
E. Sreedharan, and the experts having come to a particular conclusion, it is
very difficult then to say that the Government, in accepting such Expert
Committee Report, could be said to have behaved arbitrarily. On this ground
alone, we set aside the judgment of the High Court, as also the review
judgment.
10)The
appeals are allowed in the aforesaid terms.
11)The
Writ Petitions that are pending in the High Court may be disposed of within a
period of six months from today.
.................................. J. (ROHINTON
FALI NARIMAN)
.................................. J. (NAVIN
SINHA)
.................................. J. (INDIRA
BANERJEE)
New Delhi;
September 22, 2020